Madong Hydropower Plant

Madong Hydropower Plant is located in Madong village, North Toraja County, South sulawei Province, Indonesia, which is a runoff plant. The whole structures include head works, intake, headrace tunnel, surge tank, penstock and plant area, with the normal pool level of 955.00m, normal tail water level of 836.00m, designed water head of 112.98.00m, generation quotative flow of 16.5m3/s and installed capacity of 15MW.
We mobilized for Madong Hydropower Plant in March, 2020 and the construction of main works were started in September, 2020. The Plant was initially filled with water in December, 2021 and was put into operation in March, 2022. This project has perfectly explained our company’s business philosophy of "general contracting, optimum design, short construction period, low price, and honesty and trustworthiness".
Moreover, Madong Hydropower Plant also successfully adopted the operation mode of overseas labor services.